A Call To Petition The State of Oregon For More Education Funding

Dale Fisher sent this out and asked for it to be posted.

Dave Strahan and I chatted via email today several times, and he has made a good point that I wanted to share and get sent out.  Would it be possible for you to send this out (if you agree with it).  I have posted the following on my blog per Dave’s request:

Today, Dave Strahan our school board chair sent out an email with a great message, and I wanted to share it here.  This is a plea for help, and something that needs immediate action.  Will you please support Dave, no, will you support our kids and take action on this?  

We need to have every person that has given ANY thought to rightsizing, school closure, common prep., trimesters, limited busing, etc… etc… etc… to understand that while we pick at slivers, the very framing of our educational institution is being torn away,  and we need the people that asked for our votes and support to go to to stand up, take notice and help us out here.We need to understand that it doesn’t matter if we close two or three schools, it doesn’t matter what tweaks we make to our schedules, it doesn’t matter what bus routes we drop, we are looking at short term, non-effective in the big picture, cuts that will only get us a few more years until we are fighting the same fights again.

Rather than the time and energy that seems to be going into nit picking individual staff members and each other, I really think we could do our kids and our district much more good by channeling our efforts to the real, baseline problems in our district, which is lack of adequate funding from the state. Below is a note I sent to Rep. Peter Buckley, Chairman of the Education Committee in the State Legislature. 

I strongly encourage you to share his address with your peers and ask that they too, let our elected officials know that we are tired of continually cutting and gutting our school district and we look to them to help us out. Leslie and I have been involved in the cutting of this district for a decade or better. Enough is enough. We need to be heard loud and now. There is power in numbers and the squeaky wheel does get the grease!! Can I rely on your help?

Sincerely,

Dave Strahan

And now that letter…

Honorable Representative Buckley,

Please excuse the informality of this note, as I am sending it out of frustration and desperation, and striking while my emotions are hot. (and I am rushing to get to my paying job…..) I am the Chairman of the Three Rivers School District Board of Directors and our district is embroiled in, once again, a nasty game of  “what artery do we  cut  this year”,  with our budget. We are trying to make decisions we simply should not have to be making!! While my note below specifies only “local elected officials”, that is not totally fair or accurate.  I have never approached you, or our new Representative Ron Maurer on this issue, but over the years I have had a deaf ear turned to me by Carl Wilson, Gordon Anderson, Dennis Richardson and Jason Atkinson. I have personally, or as part of a group, approached all of these individuals only to be ignored or blown off.  Heck, in some cases they didn’t even know what we were talking about or give any indication of any desire to learn what we are talking about!! It is with deep frustration and heartfelt disappointment that, if nothing else, I needed to point out that our schools are dying a slow, painful death and it seems that no one outside our district knows or cares. Is there anything you or your committee might find to assist our struggling school district and the 5,000+  Rogue
Valley children that we serve??

Respectfully,

Dave Strahan

Chairman, Three Rivers School District Board of Directors

You know what?…Dave is right on the money with these statements.  Let’s put some energy into this action, as we have the legislature now in session.  Let’s make them hear from us.  You have issue with what is going on?  Do something!  Don’t sit on your hands a gripe about what decisions are going to be or have been made by someone else…let’s get the word to Salem!

Thanks and God Bless,

Dale Fisher

Leave a comment »

High School Trimester Schedule Scrapped: Loss of $500,000 In Savings

Note: The status of this post is unclear. Apparently a lot of of rumor is flying around, part of which I guess is my fault for posting what is more heresay than fact. I would be pleased to post any factual information that people send to me, or you can comment on the posts themselves.

Some people may not be aware that the Three Rivers School District includes elementary schools, middle schools and high schools. As part of the $1.19 million in budget cuts required for the 2008-09 school year, about $500,000 was to have come from re-organizing the high schools into a trimester schedule. I don’t know much about it but it is a very contentious issue. (You can read more about it at Dale Fisher’s Blog) At Tuesday’s Rightsizing Committee meeting, they said that $700,000 of the $1.2 million in cuts had been identified. Well, the trimester plan has been postponed or cancelled (I’m not sure which) for the coming year. This means that these 500 G’s must come from some place else now. Instead of $700,000 in cuts identified, the number is now $200,000, leaving $1 million in cuts that need to be identified for 2008-09. Despite the Daily Courier’s painting of the Williams School Bell Ringing Event as a victory celebration (It was not planned that way, though the occurence of events sort of made it that way. It was originally planned to be the same morning as the RSC meeting on Jan 30 but was postponed due to snow) it’s purpose was to rally the Williams community to action and raise a little money for the school. We succeeded in both endeavors.We are aware that the RSC has no real power. In fact, some believe it to be nothing more than a screen to diffuse blame from the board and Dr. Fritts when the axe finally falls. I have nothing to say about motives other than mine and those of the Williams community. We will continue to respect them and provide them and the TRSD board with factual evidence to back our claims that Williams School is a NET REVENUE GENERATING SCHOOL worthy of remaining open.As a community, Williams is prepared to meet the Three Rivers School District halfway. In fact, we have met these good people more than halfway and will continue to do so. We hope that they perform the jobs with which they have been entrusted with due diligence and a mighty conscience.

Leave a comment »

Kind Words From State Rep. Buckley, Chair of Education Committee

I sent a letter off to State Rep. Peter Buckley. He represents the Ashland area, but is also the chair of the Education Committee so I thought he would be interested in our challenges. I can’t post that letter, because I also sent it to some local people who were offended by it, and rightfully so. I did apologize to them, for the tone of the letter was contentious and distasteful. Now we have found common ground and hope to move forward. In any event, Rep. Buckely got the gist of the letter and replies:

Scott–

Thanks for your letter. We plan to hold informational hearings on how we might save our rural schools during our session in February, and from that, I’m hopeful that some ideas might come forward that we can push on for the 2009 legislature. There is, as you know, no immediate quick fix–we had to close down two of the five schools here in Ashland as well. Ruch Elementary has been able to stay open by going to four days per week and switching from K-6 to K-8, and by enticing homeschoolers to come back into the school.

Please keep me informed, and if any solid proposals surface, I will push as hard as I can to move them and keep rural schools going in Oregon.

Thanks & Onward,
PB

Leave a comment »

Rightsizing Committee Meeting Tonight Jan 30-Cancelled, Not Rescheduled Yet

Just got word that the Rightsizing Committee meeting tonight has been cancelled. No new date yet. Stay tuned.

Leave a comment »

SAVE WILLIAMS SCHOOL BELL RINGING RALLY POSTPONED

Sad, but true. We are postponing the rally until sometime next week. Snow is forecast for 1000 feet tomorrow morning and looks terrible through next Wednesday so we will wait and see how the five day forecast develops going into the weekend. Even if the weather changes and schools are open in the morning, it’s just too touch and go (and too much work to talk to and email people) to operate on such a slim time margin. Our hopes are to have it as early next week as weather permits. I will update on the blog as soon as we know anything definite.

Meanwhile, plan to attend the Rightsizing Committee meeting tomorrow night at 5:30 at the district office. 8550 New Hope Road, Murphy. Turn onto New Hope between the Veterinarian clinic and the gas station.

Leave a comment »

Will Williams School Rally Happen?-Depends On The Weather

Whether or not the Save Williams School Bell Ringing Rally takes place tomorrow, Jan 30, 7:30 AM, as planned depends upon the weather. If the schools are open, the rally will go on, whether or not KOBI TV can make it. The forecast doesn’t look promising, but we will stay tuned. As the weather shapes up tonight, we may get a better picture of what to expect when dawn breaks. The school district makes the final decision and that can be found at:

www.threerivers.k12.or.us

Then click on School closures/Delays on the menu bar on the left. Or call 862-3111.

If the event is cancelled, please still plan on attending the Rightsizing Committee meeting tomorrow night, Wed Jan 30, at 5:30 PM at the District Office. 8550 New Hope Rd, Murphy. Turn on New Hope Rd, which is between the Veterinarian’s office and the gas station in Murphy. The district office is across from Lincoln Savage Middle School.

Leave a comment »

Save Applegate School Community Forum Applegate School Gym Thursday, February 7th 7PM

Our neighbors at Applegate School are having a forum on Feb 7. I’m thinking that we should support each other, Williams and Applegate, and let the RSC and board know that we support them in creating a solution to keep all of our historic and cherished schools open. In dusting off some old adages such as “Where there’s a will, there’s a way” and “Build it and they will come” we can create a powerful vision to move toward. Our little corner of Jefferson is endowed with brilliant minds. In these times of globalization, we all know what “flexibility” really means. So, let’s approach our school board, composed of citizen volunteers by the way, and the rightsizing committee (volunteers all), and join them in creating the only real solution, the solution that resides in our hearts and our minds, that of keeping all the school open. We are brilliant, we are flexible. We can do it.

AUSTERITY-YES; CLOSURES-NO!

Leave a comment »

The Word Is Spreading: Austerity For All-Yes; Closures-No!

I just got a nice note from Dale Fisher, a high school teacher in the district and author of a great blog called TRSD Wroingsizing at www.trsdwrongsize.blogspot.com. He’s got alot of information and perspective worth listening to. Please look at the cost estimates for the schools that he has posted and take a hard look at them. I believe that we can keep all the schools open if we adopt realistic austerity measures across the board, and not resort to the amputation scenario developing in the district’s budget office.

Check out the thread started on a local forum at ILoveGrantsPass.com.

We can’t let this debate turn into a desperate scrum among Wolf Creek, Applegate, and Williams schools. We can create a solution that will keep all schools open. You know the Charles Dickens line about “The Best of Times, The Worst of Times?” Well…? These are going to be the good old days for the present generation of school kids. Our good old days (I’m 42) are past. What about the kids? I have studied the proposed cost estimates for Williams School and found them to be very amenable to alteration, creating a much more reasonable fiscal scenario once the creative padding has been eliminated. (Do they still call that “pork barrel politics”?) Other schools need to do the same with the proposed cost estimates devised for them. Our current budget director, David Marshall, is leaving on April 1 to take a job in California. His attention is elsewhere, but we will still live here when he is gone. The school board and rightsizing committee members will all live here when he is gone. Let us remember the minutes of the November 2007 TRSD board meeting:

“Business Manager David Marshall presented the board with the 2008-2009 budget calendar. He said the first budget committee meeting was scheduled for May 2008. The final fiscal year payment from the Department of Education was not until May 15th so he could not build the budget before that time. Member Weaver moved to approve the proposed budget calendar. Member Meier seconded.

Discussion followed on having the first meeting so late. Member FMeier stated she would like to see the “Priority Driven Budget Process” brought back. She felt it gave the community a greater voice in the process. Business Manager Marshall stated that there was only about 5-6% of the budget that was fluid. The motion carried unanimously.”

Let us do what needs to be done by those of us who live here and will continue living here long after Mr. Marshall, Superintendent Fritts, and Dick Withycombe (RSC consultant from Portland) are long, long gone. Let us roar in a collective voice, “Keep all our schools open!” With that clear goal in focus, we can move forward and do what needs to be done. These are the good old days.

Leave a comment »

Important: Updated Three Rivers School District Cost Estimates For Williams & An Alternate Cost Estimate

Sorry folks, WordPress mangled my formatting. I’ll try to clean it up at some point. But you can read the post and get the points. 

This is the updated version of cost estimates for Williams School. Original numbers appear below in bold text and comments by the independent civil and structural engineer, Scott Pingle of Kas & Associates Engineering Services, appear in italics. I have some comments at the bottom in bold caps. 

Projects – Exterior

Description

Architect Estimates

Remarks 1.0 Parking lot  Asphalt overlay at parking lot, playground, and bus turn-around areas $ 72,000 Reduce dust and mud; grading required to get water into catch basins and then into drainage ditch

The basement flooding issue has almost nothing to do with the gravel parking lot. The roadside ditch has been re-constructed to prevent water from the ditch to enter the parking lot and contribute to possible flooding. Almost all of the water that enters the basement comes from underground up through the slab and the sump pump sumps. Adding impervious area (asphalt) to the parking areas can also create drainage issues and storm water quality issues. The existing gravel area appears to be in good condition and could continue to serve the school adequately with some minor maintenance. If accessible parking is an issue, those particular parking spaces only could be paved at substantial cost savings.

2.0 ADA The gym currently does have an ADA accessible entrance from the interior asphalt courtyard and the courtyard does connect to the parking area on the north side of the building. It seems that proper signing could easily direct people to appropriate parking spaces and into the gym and the rest of the school. 

On 12 Dec 07, architects Crow and Clay believed that our estimate for ADA work was inadequate

2.1 Construct ADA concrete ramps at two entrances at the gym area. Presently persons in wheelcharis must maneuver behindthe school, through gravel.

$ 5,000This was item 2 on the original document.

2.2 Construct ADA ramp at front entry$ 30,000 This is item 12 on the original document.

Wheelchair cannot travel to the schools’ officeA ramp of this nature would destroy the look of the front of the school and would have to be at least 60 feet long because of the height and the required landings. There is an existing ramp in the rear of the school building that functions, even though it does not meet ADA standards.

Exterior Siding/Windows

2.?Install thermo-pane glass; replace/paint existing siding on main buildingNo item number assigned $ 122,000 To be done with 9.0

This $122,000 expense was item 3.0 on the original document and now resides in Section 2 with no item number.

If there are “several areas” where wind driven rain enters the wall cavities, why not just take care of those specific locations with proper maintenance and verify if there really is a problem or not, instead of assuming there is a problem?

3.0 Replace roofs

On four portable classrooms and classroom addition$ 22,000 This was item 4.0 on the original document.

4.0 Upgrade PE/athletic fieldsInstall irrigation system; provide better outdoor facilities$ 36,000 This was item 5.0 on the original document.

5.0 Replace storage shedFor hazardous material$ 2,000 This was item 6 on the original document.Present one is beyond repair

6.0 Install fenceSix foot chain link with two gates. Enhance security and improve appearance.$ 6,000 This was item 7 on the original document.

7.0 Replace seven exterior doors$ 15,000 This was item 9 on the original document.Do with 4.0, above.

8.0 Install additional security LightsLights, alarmed classrooms, motion detectors. As part of district wide upgrade effort$ 7,500 This was item 10 on the original document.

9.0 Remove underground oil tankInfringes upon playground area; prohibits expansion of restrooms.$ 63,000 This was item 11 on the original document. $40,000 of this estimated expense is only IF CONTAMINATEDSOIL IS DETECTED AND REQUIRES ABATEMENT.Pipe runs under main building; price assumes that soil is not contaminated

10.0 Paint exterior$ 54,000 This is item 13 on the original document.See 4.0, above

11.0 This item has been left blank but is item 14 on the original document and has been moved to item 15 on this document.Gym Roof Seismic Retrofit Referenced by architects Crow and Clay on 12Dec07

12.0 Refurbish Track Area$ 9,500 This is item 8 on the original document.

13.0 Architect’s Fees This item has been left blank but the expense appears in the subtotal as $25,569, $3,519 higher than the original estimate of $22,050. The reason it is higher is because it was calculated at 2% of the subtotal AFTER the contingency of 10% and the yearly estimated cost escalation of 5% were added to the subtotal.

15.0 Gym Roof Structural Reinforcement$ 70,300 This is item 14 on the original document.

During my site visit, I inspected the roof structure and the Bowstring Trusses in the gymnasium. All of the rafters, blocking, bracing and the trusses appear to be in excellent shape. All the bolts I check were tight and I found no cracks, checks, deterioration or deformation in any of the wood members. There were a few spots where there had been a leak in the roof at one time, but the structural members have not been affected by it and appear structurally sound.It is true that the combination of three factors (changes to loading, analysis methods and timber stresses) results in an overstressed condition for most bowstring trusses. (See the attached article). The concern for this truss design and most of the issues with these trusses occur during very heavy and rare snow events. It is also true that this structure has been safely standing and serving its intended use for over 50 years and has experienced many heavy snow and severe weather events without incident and remains in very good condition.The local Lorna Byrne gymnasium roof collapse in 1995 and the history of bowstring trusses in general certainly does warrant concern and it would be prudent to consider upgrading or reinforcing the trusses at some point and until that time comes, continue to monitor the trusses as is being done now and be cautious of severe snow events.

16.0 Install Site Drainage System$ 103,000 This is item 15 on the original document.

The ditch work along the highway has already been done and most of the other work described is a huge waste of resources. The real problem with the basement flooding is NOT from surface water, it is from abnormally high ground water levels. It is my understanding that during these admittedly rare events, the water remains in the basement for only a couple of days. Many areas around the world routinely flood and much more often that what have to be dealt with here (Venice, Italy and New Orleans).The basement has concrete walls and floors and the only structural elements that could be damaged by water are the large wood posts. Having the bottom of the wood posts in water for a couple of days will not cause them to deteriorate as long as they are dried out again after the event is over, plus it is quite simple and inexpensive to check them and replace them if need be. The non-structural elements in the basement could be minimized, shelving could be changed to steel racks and mechanical equipment could be set 24”

Leave a comment »

Important: Updated Three Rivers School District Cost Estimates For Applegate

Facility Improvement Projects
Applegate

Projects – Exterior

Activity/Location

Description

District Estimate

Remarks

1.0

Raze old building

$ 200,000

Use space for addl parking and playground

2.0

Siding

New siding on west and east ends of gym

$ 25,000

3.0

Replace exterior door and panic h/w

South side of gym

$ 2,000

4.0

Re-roof four portable classrooms

Aloso cafeteria/kitchen and concession shed

$ 124,875

5.0

Install exterior doors for office and classrooms

For fire safety in portables

$ 6,000

6.0

Asphalt front parking lot and playground

Additional parking; reduce dust

$ 107,250

7.0

Upgrade ramps/handrails to ADA standards

$ 60,000

8.0

Construct roofs over ramps

For safety and weather protection

$ 4,000

9.0

Paint exteriors

$ 68,000

10.0

Construct additional student restrooms

$ 150,000

Some students walk over 200 feet, in bad weather, to restrooms

Total Exterior Projects

$ 747,125

Projects – Interior

1.0

Replace 13 heat pumps

Next 5 – 20 years

$ 91,000

School heated exclusively by electricity

2.0

Gym ceiling

Insulate and cover with interior finish

$ 68,000

3.0

Retrofit lighting

Lights and ballasts

$ 57,000

4.0

Paint building interiors

$ 52,500

5.0

Retrofit boys and girls shower rooms

Girls have no lockers

$ 32,000

6.0

Replace vinyl floor covering

$ 7,950

7.0

Replace carpet in 12 classrooms

Existing carpet is 28 years old

$ 33,150

8.0

Install water to four portable classrooms

$ 9,000

9.0

Additional electrical receptacles

$ 28,200

Total Interior Projects

$ 378,800

Subtotal All Projects

$ 1,125,925

Contingency (@ 10 percent)

$ 112,593

Subtotal

$ 1,238,518

Escalated Costs at 5 percent per year

$ 1,512,636

Permits (@ 2 percent)

$ 30,253

Subtotal

$ 1,542,889

Architectural/Engineering Fees/Reimbursables @ 15 percent

$ 231,433

Total Budget Estimate

$ 1,774,322